Log in

Bayfield to reopen after construction

Bayfield Drive at Ashbrook Wash will be reopened on Friday, June 17, after being closed several months for construction of a drainage culvert through the wash. Paving over the culvert was completed on Thursday.

There is a one day closure tentatively scheduled for Friday, June 24th to adjust two manholes to grade underneath the pavement section.

The Town also intends to mill and overlay the remainder of Bayfield Drive and portions of Hamilton Drive with the 2016 pavement Management Program scheduled for the week of October 10th while schools are on their fall break.

You must be a member to read this story.

Join our family of readers starting at $5 for your first month and support local, unbiased journalism.


Already have an account? Log in to continue.

Otherwise, follow the link below to join.

Please log in to continue

Log in
I am anchor

Bayfield to reopen after construction

Posted

Bayfield Drive at Ashbrook Wash will be reopened on Friday, June 17, after being closed several months for construction of a drainage culvert through the wash. Paving over the culvert was completed on Thursday.

There is a one day closure tentatively scheduled for Friday, June 24th to adjust two manholes to grade underneath the pavement section.

The Town also intends to mill and overlay the remainder of Bayfield Drive and portions of Hamilton Drive with the 2016 pavement Management Program scheduled for the week of October 10th while schools are on their fall break.