Log in

Crack seal shortfall

At its Thursday meeting the Town Council needed to approve an emergency expenditure of $100,000 to complete crack seal work on streets in the northwest corner of town.

Cactus Asphalt, the contractor working on the sealing project prior to a slurry seal application, found there were too many large cracks in the streets to complete the work as specified in the original agreement.

You must be a member to read this story.

Join our family of readers starting at $5 for your first month and support local, unbiased journalism.


Already have an account? Log in to continue.

Otherwise, follow the link below to join.

Please log in to continue

Log in
I am anchor

Crack seal shortfall

Posted

At its Thursday meeting the Town Council needed to approve an emergency expenditure of $100,000 to complete crack seal work on streets in the northwest corner of town.

Cactus Asphalt, the contractor working on the sealing project prior to a slurry seal application, found there were too many large cracks in the streets to complete the work as specified in the original agreement.

Development Services Director Paul Mood told the council it was found that the cracks were too numerous and too deep to be completed under the original contract.

Once the crack sealing is completed Southwest Slurry will begin work, which is scheduled to begin on May 13.

crack seal, slurry seal, street department

Share with others


Have an opinion on this story? Click here to send a letter to our editors.

Comments

No comments on this item Please log in to comment by clicking here